Make the best use of Scientific Research and information from our 700+ peer reviewed, Open Access Journals that operates with the help of 50,000+ Editorial Board Members and esteemed reviewers and 1000+ Scientific associations in Medical, Clinical, Pharmaceutical, Engineering, Technology and Management Fields.
Meet Inspiring Speakers and Experts at our 3000+ Global Conferenceseries Events with over 600+ Conferences, 1200+ Symposiums and 1200+ Workshops on
Medical, Pharma, Engineering, Science, Technology and Business

Mechanical Technique for Raising an Obelisk

Shiells JE*
US Government, 1401 Clearview rd, Edgewood MD, USA
Corresponding Author : James E Shiells
US Government, 1401 Clearview rd
Edgewood MD, USA
Tel: 410 676 0640
E-mail: [email protected]
Received: June 09, 2015 Accepted: July 29, 2015 Published: August 02, 2015
Citation: Shiells JE (2015) Mechanical Technique for Raising an Obelisk. J Appl Mech Eng 4:174. doi:10.4172/2168-9873.1000174
Copyright: © 2015 Shiells JE. This is an open-access article distributed under the terms of the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.
Related article at Pubmed, Scholar Google

Visit for more related articles at Journal of Applied Mechanical Engineering

Abstract

A simple technique is outlined which may answer the mystery of how the Egyptian obelisks were raised to their upright position. This technique relies on a mechanical ram which is characterized by equations that are derived in this article. The mechanical ram is basically a leverage device which would enable the ancients to apply a very large force with only a minimal input force. A paper analysis is developed to show how this technique may have raised the heavy 130,000 kg Thutmose obelisk upright, although the procedure would have been painstakingly slow. Note however, that no case is made here that the Egyptians actually used this technique.

Keywords
Mechanics; Obelisks; Archaeology
Introduction
A paper analysis is presented of a proposal to erect the moderate size Thutmose obelisk. This paper compares the turning moment to set Thutmose upright with the theoretical available force that could be obtained from the force multiplier method described. This technique depends on an unusual lever arrangement which will hereafter be referred to as a mechanical ram. The hydraulic ram could be considered as the modern functional equivalent of this mechanical ram. However, an important disadvantage of the mechanical ram is the minute working stroke as compared to a hydraulic ram. Therefore such a mechanical ram would have to be repositioned (reset) many times in order to ratchet the obelisk centimetre by centimetre to the final upright position.
First, some background material is presented which motivated this study including a brief description of the current thinking about this problem. Then the mechanical ram is described in detail, followed by an estimate of force required to raise Thutmose. Finally, some practical considerations are explored including the application of a finite element analysis Bathe [1] to establish the practically of the theoretical proposal.
Background
The PBS television program NOVAR in “Secrets of Lost Empires: Obelisks” Barnes [2] made the public aware of the mystery of how the Egyptians raised the massive obelisks to the upright position. Levers could raise the obelisks to a certain height but eventually the raising height limits the availability of pivot points as well as the amount of force that can be applied to the end of the lever. Archeologists Englebach [3] were well aware of this problem many years ago. Later Chevrier [4] a method was proposed by which an earthen (sand) ramp was used. The idea was to shove the obelisk (backwards) up the gradual sloping end of the ramp and then have the base of the obelisk go over the steep end of the ramp under control of ropes until it settled on the pedestal rock. This method is sometimes referred to as the “sand funnel” method which is said to be unproven Arnold [5].
A very interesting discovery was made during the production of the PBS video Barnes [2]. When the crew went to the “obelisk graveyard” in Tanis, Egypt, they found pedestal stones with a turning groove along with associated abandoned obelisks. Figure 1 shows a drawing of such a stone supporting the edge of the obelisk base. This kind of stone would be absolutely necessary to prevent slipping or twisting if a method were known for pushing the obelisk upright from the horizontal position like the technique described here. The “sand funnel” technique envisions that the obelisk is set down at a high angle in which slipping would be unlikely, hence no need for a turning groove. In chapter 3 of his book, Wirsching [6] present a number of mechanical proposals for solving this erection problem. None of these methods are remotely similar to the technique outlined in this paper. Most of these methods depend on brute force with little attention to mechanical advantage except for one. This one is similar to the “sand pit” method which represents the latest thinking. This idea Cort [7] is that the obelisk is slowly lowered while turning into the upright position by allowing the supporting sand under the obelisk base to escape in a controlled manner. This technique however requires the obelisk to be contained in a giant sand box and is not universally accepted.
Mechanical ram description
Figure 1 show the essential features of the mechanical ram along with the associated force vectors. Two rigid beams (A and B) are situated between two stationary surfaces about which they are free to rotate but not slide (pivot only). The beams are oriented at the angle (phi) ϕ off the vertical as shown. Where these beams meet is the point where beam C is used to apply the force F. This force F compresses both beams A and B equally. From an examination of the force diagram it follows that each of these beams must resist with a horizontal force component of magnitude F/2. With further analysis of the force diagram it also follows that the vertical force component is given by equation.
Fvert=( F/2 ) cot (ϕ) (1)
The mechanical advantage (MA) of the system is defined as the ratio of the vertical force component to the applied force F as shown by equation 2.
MA=Fvert/F (2)
Combining equation 1 with equation 2 yields equation 3 which defines the mechanical advantage in terms of the angle ϕ.
MA=.5 cot (ϕ) (3)
From equation 3 it becomes apparent that very high values of mechanical advantage (MA) may be obtained with this system if small values of angle ϕ are used. However, the lower value of the starting angle ϕ implies that the useful working stroke (WS) becomes smaller. Figure 2 illustrates how the working stroke for a unity length beam is calculated.
Since two beams are involved in the mechanical ram, the maximum working stroke is given by equation 4.
WS=2 {1.0-cos (ϕ)} (4)
Table 1 list several values of mechanical advantage (MA) and working stroke (WS) as a function of the angle phi.
For example, if two 6.1 m beams are set at the initial angle of ϕ=4 degrees it follows from Table 1, that a mechanical advantage of 7.1 with a working stroke of (6.1×100× .00488 ) or 3 cm is available. Referring to Figure 1, this means that a force F of 10000 N will result in a vertical force Fvert of 71000 N with a maximum lift of 3 cm. When the ram advances the value of phi decreases which means the MA becomes higher and the required input force for a constant load drops accordingly. While moderately impressive for a force multiplier it clearly falls short of the task of raising Thutmose which is approximately 130,000 kg. However, the situation changes dramatically when consideration is directed toward a serial mechanical ram configuration. Figure 3 show two mechanical rams placed in series.
In this arrangement a force F on the first ram (beams C and D) is magnified by MA before being applied to the second ram (beams A and B) where it is magnified again by MA. In order for the second ram to complete its full working stroke it is necessary for the first ram to be used several times. The advance of the second ram must be locked temporarily else it would snap back when resetting the first ram. In raising an obelisk, this would mean locking each incremental increase of elevation with a temporary support or “follower” beam.
Table 2 is a repeat of Table 1 except that the values of MA are squared to describe the features of the serial mechanical ram.
As an example of the capability of the serial mechanical ram, consider the case of four 5 m beams (A, B, C, D) in Figure 3 with a starting angle ϕ equal to 5 degrees. From Table 2 the mechanical advantage (MA) is now 32.5 and the working stroke (WS) is (5× 100× .00762) or 3.8 cm. Referring to Figure 3, this means that if a force (F) of 5000 N is applied, then a lift Fvert of 162,500 N can be expected. The first ram (C/D) would have to be reset several times so that the second ram (A/B) could complete the 3.8 cm working stroke. The order of magnitude of force available from such a device suggests it may be up to the challenge of raising Thutmose.
Obelisk force estimations
The analysis of the force required to turn the obelisk to the upright position follows: The Thutmose I obelisk Wirsching [6] is approximately 20 m long and a mass estimated at 130,000 kg. Clearly, the force required to upright the obelisk depends on where the force is applied as well as the angle of inclination theta (θ) of the obelisk. The angle θ being 0 degrees when the obelisk is on its side and θ is 90 degrees when it is upright. In order to make these estimates it is first necessary to calculate the turning moment (Mo) of the obelisk as a function of the inclination angle θ. Figure 4, represents the obelisk at some intermediate angle θ. For modelling purposes, a simplifying assumption is made that the 130,000 kg mass is distributed uniformly along the 20 m length. In reality, the actual obelisk tapers slightly toward its top and its centre of gravity would therefore be closer to its base. This assumption of uniform density would make the modelled obelisk more difficult to turn upright than the actual Thutmose I. Figure 4 illustrates the moment arm length L about which the weight W acts hence the turning moment Mo is given by equation 5 where Len is the length and W is the weight of the obelisk.
Mo = .5 Len W Cos ϕ (5)
Table 3 list the turning moments as calculated by equation 5 for various values of the inclination angle However, or very high angles, (i.e. 75 degrees or greater) the turning moment is overstated by equation 5. This is because an increasing fraction of the obelisk mass acts to counter-balance the mass on the other side of the pivot point.
Once the turning moment (Mo) is established, it becomes convenient to calculate the single force (F) required to balance the obelisk weight depending on the location where the force is applied. This force (F) is calculated by dividing the turning moment (Mo) by the turning arm (L) length. Figure 5 show the relationship between the arm length (L), the point of force application (x) and the angle of inclination ϕ.
Table 4 list the results obtained for the case of single force acting at a point 19-1/6 m from the base of the obelisk. Ideally, the force should be applied, as nearly as possible, perpendicular to the side of the obelisk. In practice, the point of force application would likely have to be lowered as the obelisk rises. This would allow for shorter and more reasonable length beams.
Single serial ram application
The above tables show the order of magnitude of force (600,000 N) required by a mechanical device to upright Thutmose. The serial mechanical ram example Figure 3 described earlier would be capable of about 487,500 N lift with only 15,000 N of input force. It illustrates how the serial mechanical ram might be employed to upright the obelisk. The obelisk is shown pivoting on its turning block at an angle of 20 degrees. The rigid beams (A,B,C,D) which make up this serial mechanical ram are shown at an exaggerated starting angle (ϕ=10) for clarity. Likely some initial obelisk angle of perhaps 10 degrees or so could have been achieved through the use of regular lever beams. This is because a number of levers could be operated at the same time given the obelisks near horizontal position. For the postulated obelisk it is seen from Table 4 that a force of 625,033 N would be required to lift the obelisk when it is at 20 degrees. From Table 2 if the mechanical ram were set up with a starting angle (ϕ) of 4 degrees, then a mechanical advantage (MA) of 50.4 could be expected. This means that an input force of (625,033/50.4) or 12,400 N need be applied manually by a group of men pulling on a rope. In this example the beams shown to scale are about 4 m long. The working stroke (WS) may be calculated by using Table 2 and is found to be (4 × 100 × 0.00488) or only about 2 cm.
Multiple serial ram application
When multiple mechanical rams are used in parallel then a substantially longer stroke is possible. For example, if four mechanical rams replaced the single ram then each ram would require a mechanical advantage (MA) of one fourth of that of the single ram. In this case that would be a mechanical advantage of 50.4/4 or 12.6. From Table 2 or thru the use of equation 3 the starting angle would now be 8 degrees rather than the original 4 degree starting angle for the single ram. From Table 2 the new working stroke (WS) for the unit beam is found to be 0.01946. Therefore the working stroke for the quad system is (4 × 100 × 0.01946) or about 8 cm. This quad system would require four separate applications of the 12,400 N force. The width of Thutmose would easily accommodate such a quad system of parallel serial rams.
Finite Element (FE) Simulation
One of the rams in the quad system is examined with the finite element program ADINAR in order to check the above theory. The purpose of the FE analysis is not only to verify the predicted force against the obelisk but also to assess the stress on the beam. In the FE simulation it was assumed that cedar beams make up the mechanical ram. This is because in Arnold [5] it was stated that cedar beams were used to prop up a wall in a pyramid during ancient construction. The mechanical properties of yellow cedar (12% moisture) were taken from ref. 8. In beam A (like beam B) is overwhelmingly subjected to the most stress when lifting the obelisk. The FE analysis was therefore directed to beam A. Figure 6, shows (not scaled for clarity) the physical configuration for the analysis of beam A. The load is one half of the input force (12400 N) times the mechanical advantage of the first mechanical ram (C/D). This works out to be (0.5×12400×√12.6) or 22010 N. The cedar beam has a square cross-section of 30×30 cm and is 4 m long. The boundary conditions are the same that were assumed for Figure 1.
In the earlier development of the ram equations, it was assumed that rigid beams connected the contact points. The red line in Figure 6 represents such a one dimensional beam between the peak pressure points. The configuration was designed so that the angle of this equivalent beam was degrees above the horizon, although the cedar beam is only 4 degrees.
FE Simulation Results
The color coded stress results of the FE simulation are shown in Figure 7a. This confirms that the maximum contact force (color light green) occurs as indicated by the red arrow heads in Figure 6. It also shows that the cedar beam is not at all over stressed. The maximum stress is listed as 8,375 kPa while the maximum compression limit for cedar is more than 5 times greater at 43,500 kPa.
The FE program also provided the nodal contact forces between the end of the cedar beam and the obelisk surface i.e.CS1. Figure 7b is a listing of these nodal forces which resulted from the 22010N load. The non-zero nodal forces were, as expected, on the lower face of the beam end as depicted by the red arrow head in Figure 6. The sum of these nodal forces added up to 15.4 E04 N. The mechanical advantage (MA) readily follows by dividing this force by twice the input load of 22010 N. This value of 3.49 compares favorably with Table 1 (phi=8), which predicted 3.55 based on the elementary vector analysis (Figure 7c).
Conclusion
In conclusion, it has been demonstrated through the use of vector analysis and computer simulation how the ancients may have brought to bear the tremendous force necessary to upright the 130,000 kg obelisk. The technique outlined in this paper required only a direct force of approximately 12,400 N. Figure 8 shows the basic serial ram setup although the required “follower” beam which locks each elemental increase in elevation of the obelisk is not shown. An advantage of this slow gradual procedure is that it allows time for care that the obelisk does not flip to either side during erection. When the obelisk is nearly upright, a team controlling ropes Cort [7] attached to the top has proven effective in the final stage of the ascent. The technique outlined in this paper may also have been used by the ancients to move massive building blocks. While this technique required incredible patience, this task would pale by comparison to the job of shaping the obelisk from solid granite with only primitive tools.
References







Tables and Figures at a glance

Table icon Table icon Table icon Table icon
Table 1 Table 2 Table 3 Table 4

 

Figures at a glance

 

Figure Figure Figure Figure Figure
Figure 1 Figure 2 Figure 3 Figure 4 Figure 5
Figure Figure Figure Figure Figure
Figure 6 Figure 7a Figure 7b Figure 7c Figure 8
Select your language of interest to view the total content in your interested language
Post your comment

Share This Article

Relevant Topics

Article Usage

  • Total views: 11678
  • [From(publication date):
    August-2015 - Nov 18, 2017]
  • Breakdown by view type
  • HTML page views : 7901
  • PDF downloads : 3777
 

Post your comment

captcha   Reload  Can't read the image? click here to refresh

Peer Reviewed Journals
 
Make the best use of Scientific Research and information from our 700 + peer reviewed, Open Access Journals
International Conferences 2017-18
 
Meet Inspiring Speakers and Experts at our 3000+ Global Annual Meetings

Contact Us

Agri & Aquaculture Journals

Dr. Krish

[email protected]

1-702-714-7001Extn: 9040

Biochemistry Journals

Datta A

[email protected]

1-702-714-7001Extn: 9037

Business & Management Journals

Ronald

[email protected]

1-702-714-7001Extn: 9042

Chemistry Journals

Gabriel Shaw

[email protected]

1-702-714-7001Extn: 9040

Clinical Journals

Datta A

[email protected]

1-702-714-7001Extn: 9037

Engineering Journals

James Franklin

[email protected]

1-702-714-7001Extn: 9042

Food & Nutrition Journals

Katie Wilson

[email protected]

1-702-714-7001Extn: 9042

General Science

Andrea Jason

[email protected]

1-702-714-7001Extn: 9043

Genetics & Molecular Biology Journals

Anna Melissa

[email protected]

1-702-714-7001Extn: 9006

Immunology & Microbiology Journals

David Gorantl

[email protected]

1-702-714-7001Extn: 9014

Materials Science Journals

Rachle Green

[email protected]

1-702-714-7001Extn: 9039

Nursing & Health Care Journals

Stephanie Skinner

[email protected]

1-702-714-7001Extn: 9039

Medical Journals

Nimmi Anna

[email protected]

1-702-714-7001Extn: 9038

Neuroscience & Psychology Journals

Nathan T

[email protected]

1-702-714-7001Extn: 9041

Pharmaceutical Sciences Journals

Ann Jose

[email protected]

1-702-714-7001Extn: 9007

Social & Political Science Journals

Steve Harry

[email protected]

1-702-714-7001Extn: 9042

 
© 2008- 2017 OMICS International - Open Access Publisher. Best viewed in Mozilla Firefox | Google Chrome | Above IE 7.0 version
adwords