Make the best use of Scientific Research and information from our 700+ peer reviewed, Open Access Journals that operates with the help of 50,000+ Editorial Board Members and esteemed reviewers and 1000+ Scientific associations in Medical, Clinical, Pharmaceutical, Engineering, Technology and Management Fields.
Meet Inspiring Speakers and Experts at our 3000+ Global Conferenceseries Events with over 600+ Conferences, 1200+ Symposiums and 1200+ Workshops on Medical, Pharma, Engineering, Science, Technology and Business

Pre-grouting for Leakage Control and Rock Improvement

Subash TR, Abhilash Urs KR, Ananth M* and Tamilselvan K

L&T Construction, Chennai, India

*Corresponding Author:
Ananth M
L&T Construction, Chennai, India
Tel: +919566913277
E-mail: [email protected]

Received April 11, 2016; Accepted April 26, 2016; Published April 28, 2016

Citation: Subash TR, Abhilash Urs KR, Ananth M, Tamilselvan K (2016) Pre-grouting for Leakage Control and Rock Improvement. J Civil Environ Eng 6:226. doi:10.4172/2165-784X.1000226

Copyright: © 2016 Subash TR, et al. This is an open-access article distributed under the terms of the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.

Visit for more related articles at Journal of Civil & Environmental Engineering

Abstract

In underground construction, ground water inflow and rock mass stability has been a challenging problem. Especially the tunnels constructed below ground water table are often exposed to risk of ground water inflow. Protection of underground structures against water ingress and rock mass failure is of paramount importance during construction as well as operation of the tunnel. Risks associated with these hydrogeological issues often pose challenge to tunneling engineers. Mitigation of these risks by means of pragmatic measures such as pre-grouting can improve the rock mass strength and restrict the water ingress to acceptable levels. The primary purpose of pre-grouting is to improve the rock mass strength and establish an impervious zone around the tunnel periphery, thus leading to reduced support system and permeability of rock mass. The aim of this article is to discuss the concept of pre-grouting as an effective mitigation measure for leakage control and rock mass improvement which is being successfully implemented in many countries.

Keywords

Pre-grouting; Permeability; Rock mass stability; Tunnels

Introduction

Control of groundwater leakage and rock mass stability has always been a challenging task for tunneling engineers. Slowing down of the tunnel advance rates, installation of support systems, durability of the lining systems and hindrance to safe operation of the tunnel are some of the key risks faced in most of tunneling projects due to water ingress and rock mass instability. These problems often lead to schedule delays and cost overruns. Envisaging the magnitude of these highly variable risks and developing appropriate measures to mitigate these risks is the key to successful construction of a tunnel. General perception is to consider grouting as a contingency measure, but pre-grouting has been successfully adopted in many countries to mitigate the aforementioned risks beforehand. A properly planned pre-grouting approach can improve the rock mass strength and establish an impermeable zone around the tunnel periphery [1]. The recent development in grouting materials and grouting technology are increasing the possibility to achieve tangible improvements (impermeability and strengthening) in rock quality by pre-grouting [2]. This article presents some guidelines on pre-grouting methodology, material selection, concept of leakage control and rock mass improvement with illustrations.

A conceptual explanation of grouting

Pre-Grouting is a process of injecting grout material into boreholes drilled into the rock mass around an excavation, with the purpose of sealing any fissures or joints that intersect the borehole. Thus, pre-grouting results in a less permeable and more stable rock mass around the excavation. The main objective of the pre-grouting is

• To enhance the rock mass strength thus leading to reduced support system and increased productivity.

• To reduce the rock mass permeability and thereby control the water leakage to the acceptable levels.

Permissible leakage rate

The intensity of leakage into a tunnel depends on factors such as permeability of the surrounding rock mass, permeability of the tunnel lining, and groundwater conditions [3]. The permissible leakage rates along a cavern or tunnel alignment system must be decided prior to the excavation phase by considering the actual circumstances into account. Permissible leakage rate for tunnels are often fixed by the owner for the safe operation of a particular tunnel. International standards have been established for the specification of permissible leakage rates. A compendium of permissible leakage rates is listed in Table 1 [4].

Standards Moisture Characteristics
Completely Dry Largely Dry Capillary penetration
  Discharge (litre/sq.m/day)
ITA tech REPORT- 2013 Nil 0.0199 (<0.02) 0.02
German Rail AITES - 2001 Nil 0.05 0.1
Haack -1991 0.01 0.05 0.1
ITA REPORT- 1991 0.001 0.01 0.1
Note: Description of particular moisture characteristics varies as per the corresponding references.

Table 1: Permissible leakage rates as per International standards.

Pre-grouting pattern

In underground projects detailed hydrogeological assessment is implemented prior to arriving at a feasible pre-grouting pattern. Probe and grout hole orientations are often selected and further optimized to cross as many of the rock fractures as possible. Holes should be orientated to intercept rock fractures of greatest potential of impact to the tunnel and at angles which are near normal as possible to the feature’s strike and dip. Generally grout hole of spacing 1 m to 1.5 m with angle of 4 to 7 degree and length of 15 m to 25 m is adopted [5].

Pre-grouting strategy

A balanced approach to pre-grouting has the potential to reduce the ground water inflow substantially. Strategy for pre-grouting as per Gunnar is explained below [6].

1. A predetermined number of probe holes are drilled ahead of the tunnel face.

2. A water loss test is carried out by water pressurizing of the holes.

3. The water losses are expressed in terms of Lugeon (L). The measurements give an indication of the water tightness of the rock and are taken into account for determination on the type of grout material that shall be used.

4. The probe holes are grouted until a predetermined counter pressure is achieved.

5. If leakages as measured in the probe holes are greater than acceptable, a new round of control holes between the first ones is drilled. Water losses are measured and grouting is carried out according to the same criteria as for the probe holes.

6. The procedure is repeated until the criteria for water tightness are fulfilled.

Execution of pre-grouting

Pre-grouting is generally either done from the surface or from inside the tunnel. The method of drilling and injection of grout depends on the site conditions. In untreated rock, partial hole collapse and difficulty in retraction of drilling rods is a possibility. For this reason, one of the practices is to establish the drill holes through pipes grouted up to a certain extent. A gist of generic grouting methodology is summarized below [7] (Figure 1).

Figure

Figure 1: Pre-grouting methodology.

1. Drilling of 40-75mm diameter hole to required length and inclination as per the site condition. The pattern and spacing of the grout holes will be based on groutability test.

2. Installation of a pipe with internal diameter to fit the expandable packers.

3. Placement of packer at the very end of the pipe and injection of a cement based grout which fills the annular space between the rock and the pipe. Hardening for about 12 hours.

4. When the grout is hardened, drilling through the pipe to feasible length.

5. Placement of packer and pressure injection with appropriate cement grout for penetration into the rock mass in the drilled length of the hole. Termination criteria as per grout mix design.

6. After hardening of the injected grout, re-drilling through the pipe and injected area to design length beyond last drilled length.

7. Placement of the packer in the pipe and inject (repetition of step 5).

Grout materials

The selection of grout material is an essential part of grouting. The grout must have the ability to penetrate the fractures to seal them [8]. The selection of appropriate grout material depends on the size, frequency and configuration of the fractures and pores in the rock mass. The particle size of the cementitious material plays a key role in the selection criteria of grout. Based on the fissures size in the rock mass, grout material will be selected. Many methods such as Mercury injection, Gas expansion, Optical method and X-ray tomography methods have been developed for determining fissure size/porosity in rock mass samples.

This paper primarily focuses on cementitious grouts and hence the same has been elaborated below.

Cement: Generally to achieve the cost effectiveness, stable grouts formulated with locally available ordinary Portland cement is used. This cement has an average particle size of 45 μm and fineness of about 225 m2/kg. Micro-cement is used for finer fissures, where it is not feasible to use OPC. Micro-cement is finely grounded ordinary cement with large specific surface and fine particle size of about 15 μm. As an alternative to cement-based materials, various solutions have been evaluated as grouting materials such as colloidal silica. Colloidal silica is an aqueous dispersion of discrete colloidal amorphous silica particles. The particle size of the colloidal silica is less than 0.015 μm. A schematic illustration of different cement particles (μm) with respect to rock aperture is portrayed in Figure 2.

Figure

Figure 2: Particle size distribution.

As a general rule of thumb the type of cement can be chosen based on the groutability ratio. The groutability ratio for rock depends on width of the crack and the grain size of the grout material, expressed as shown in the formula below. For groutability ratios > 5, grouting is considered consistently possible whereas for groutability ratios < 2, grouting is not considered possible [9].

image

Water cement ratio: The properties of cement-based grouts vary with respect to w/c ratio. Generally for the grout mix, w/c ratio starts at 3:1 and is gradually thickened to 2:1, 1:1 and 0.5:1 until refusal is reached.

Additives

Different additives can be used to change the properties of the grout. The most common are superplasticizers, which are used to increase the flowability of the grout and to improve dispersion. Other additives are accelerators, non-shrink and thixotropic admixtures.

Pre-grouting - leakage control

The rock mass is a discontinuous material and its hydraulic characteristics vary widely from an impervious medium to a highly conductive zone. Permeability of rock mass is defined as the ability of a rock to allow the passage of water through its pores, fissure and joint. Generally, the amount of water flowing through a certain area can be represented by the coefficient of permeability. For rock mass, the coefficient of permeability is a function of rock type, pore size, entrapped air in the pores, rock temperature, and viscosity of water.

The primary purpose of a pre-grouting scheme is to establish an impervious zone around the tunnel periphery, where the hydraulic conductivity is reduced. This zone ensures that the all-round hydrostatic pressure surrounding the tunnel is distanced from the tunnel periphery to the outskirts of the pre-grouted zone as depicted in Figure 3 [10]. The water pressure is gradually reduced through the grouted zone and the water pressure acting on the tunnel lining can be close to nil. Studies conducted in Norway suggest that, tunneling in urban areas may be subject to a maximum allowable water inflow level of 2-4 liters per minute per 100 meter tunnel, whilst in remote areas such as subsea tunnels the maximum allowable level can be fixed to 30 litres per minute per 100 meters. Table 2 illustrates the reduction in ground water inflow due to pre-grouting in few of the Norwegian tunneling projects [11].

Figure

Figure 3: Hydrostatic pressure (a) Before pre-grouting (b) After pre-grouting.

Projects Depth (m) Requirement Result Materials
(l/min/100m)
Baneheia 20 - 40 6 - 12 1.8 Micro cement with micro silica
Storhaug 10 - 15 3 1.6 Micro cement with micro silica
Metro in Osla 20 - 25 7 - 14 3 - 8 Micro cement with micro silica
Froya 150 30 12 Standard cement with micro cement
Lunner 10 - 300 10 - 20 8 Standard cement with micro cement
Bragarness 10 - 150 10 - 30 10 Standard cement with micro silica
Hagan 6 - 60 5 - 10 4 - 19 Standard cement with micro silica

Table 2: Reduction in ground water inflow due to pre-grouting in tunnel projects.

Barton observed that pre-grouting reduces the maximum permeability by 17 times and the minimum permeability by one-tenth in rock mass. Neby have noted that for a water treatment plant at Oslo, water leakage at tunnel face reduced from 100 liters/min to 27 liters/ min due to pre-grouting [12].

Pre-grouting – rock improvement

Barton considered a 10m diameter tunnel in quartzite rock with UCS of 50 MPa under 200 m overburden to witness the effect of pre-grouting by analysing various engineering parameters before and after pre-grouting [13]. Improvement in some of the key rock mass parameters is shown in Table 3.

Parameters Before Grouting After Grouting
Rock Quality Designation, RQD (%) 30 50
Joint set number, Jn 9 6
Joint roughness number, Jr 1 2
Joint alteration number, Ja 2 1
Joint water reduction factor, Jw 0.5 1
Stress reduction factor, SRF 1 1

Table 3: Rock mass parameters before and after pre-grouting.

Thus, with these rock mass parameters, Singh and Goel noted an improvement in about 25 engineering parameters by the implementation of pre-grouting, notable few are depicted in Figure 4. A typical calculation for improvement in rock mass quality and reduction in permeability due to pre-grouting is illustrated below

Figure

Figure 4: Improvement in rock mass parameters after pre-grouting.

Rock Mass Quality, image

image [Before Pre-grouting]

Permeability, image [After Pre-grouting]

Permeability, image

image [Before Pre-grouting]

image [After Pre-grouting]

High Q-values indicates good stability and low values means poor stability. Quality of rock mass increased from 0.83 to 16.7 with the implementation of pre-grouting as seen from the calculation above. Pre-grouting enhances the rock mass strength, thereby reducing the deformation and support pressure, leading to an economical support system. As per Barton model, for the example case discussed earlier the thickness of SFRS and spacing of rock bolts reduces from 100 mm to none and 1.6 m to 2.4 m c/c respectively.

Conclusion

In this article, an effort has been made to showcase pre-grouting as an effective mitigation measure for leakage control and rock mass stability. Some of the noteworthy points pertaining to pre-grouting are mentioned below.

1. It has been noted that permeability can be reduced up to 1 lugeon using cement grout. Also, with the recent developments in grout materials, achieving permeability close to 0.1 Lugeon is possible.

2. Also, Barton observed that pre-grouting reduces the maximum permeability by 17 times and the minimum permeability by one-tenth in rock mass.

3. Neby have noted that for a water treatment plant at Oslo, water leakage at tunnel face reduced from 100 liters/min to 27 liters/ min due to pre-grouting.

4. As evidenced above, the pre-grouting effectively shifts the hydrostatic pressure from the tunnel periphery to the outskirts of the pre-grouted zone. Thus, pre-grouting can be considered to provide an effective leakage control mechanism.

5. Q value in one case has been improved from 0.8 to 16.7 because of pre-grouting; this indicates that the rock mass category has changed from ‘very poor’ to ‘good’.

6. Singh and Goel observed improvement in 25 rock parameters such as rock mass strength, modulus of deformation and support pressure reduction.

References

Select your language of interest to view the total content in your interested language
Post your comment

Share This Article