alexa
Reach Us +44-1522-440391
Production Capacity Planning with Market Share Expansion under Different Procurement Strategies | OMICS International
ISSN: 2162-6359
International Journal of Economics & Management Sciences
Make the best use of Scientific Research and information from our 700+ peer reviewed, Open Access Journals that operates with the help of 50,000+ Editorial Board Members and esteemed reviewers and 1000+ Scientific associations in Medical, Clinical, Pharmaceutical, Engineering, Technology and Management Fields.
Meet Inspiring Speakers and Experts at our 3000+ Global Conferenceseries Events with over 600+ Conferences, 1200+ Symposiums and 1200+ Workshops on Medical, Pharma, Engineering, Science, Technology and Business
All submissions of the EM system will be redirected to Online Manuscript Submission System. Authors are requested to submit articles directly to Online Manuscript Submission System of respective journal.

Production Capacity Planning with Market Share Expansion under Different Procurement Strategies

Sidi Wu* and Hisashi Onari

Department of Industrial and Management Systems Engineering, Waseda University, Tokyo, Japan

*Corresponding Author:
Sidi Wu
Department of Industrial and Management Systems Engineering
Waseda University, Tokyo, Japan
Tel: (+81) 3-5286-3192
E-mail: [email protected]

Received Date: May 12, 2016; Accepted Date: May 24, 2016; Published Date: May 25, 2016

Citation: Wu S, Onari H (2016) Production Capacity Planning with Market Share Expansion under Different Procurement Strategies. Int J Econ Manag Sci 5:345. doi:10.4172/2162-6359.1000345

Copyright: © 2016 Wu S, et al. This is an open-access article distributed under the terms of the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original author and source are credited.

Visit for more related articles at International Journal of Economics & Management Sciences

Abstract

Market share expansion strategy is usually considered by the manufacturers who intend to achieve lower production cost to extend the surviving period in mature markets where intense price competition occurs frequently. This study will discuss one manufacturer who is producing mature stage products and supplying them to product market to serve the end users. In order to produce the products, it is necessary for the manufacturer to procure the key components of the products from the component market which is on its fast-growing stage with high price fluctuation. Spot procurement and SC procurement are to be compared to find out which is a better strategy to support the manufacturer in the decision-making of production capacity. Profit rate, deficit rate and market share rate are considered as the valuation index in this study.

Keywords

Supply chain; Uncertainty; Production capacity planning; Component procurement; Market share expansion; Contract

Introduction

This paper focuses on the manufacturers who are producing the mature stage products and supplying them to the product market. In order to finish products producing, it is necessary for them to do procurement of key components from the component market. Market share expansion strategy is usually considered by these manufacturers in order to get lower production cost to extend the surviving period in such mature market with intense price competition. To expand market share, it means, manufacturers should plan more production capacity. Price increasing and short supply of components makes the manufacturers worry about low profit achievement and over investment. Especially, while the components are on their fastgrowing stage, high price fluctuation and high supply uncertainty make components procurement risk more serious. For example, like camera manufacturers in Japan, they are under such severe environments. Camera is a mature product in Japan, an image sensor can be considered as the key component of a camera, the sell price of a camera decided by the price of the sensor. Especially, purchasing cost of a high-class sensor occupies a large proportion of the sell price of a high-class camera (Figure 1). Image sensors are also used to produce fast-growing products such as surveillance camera, security systems for automobile and so on.

Figure

Figure 1: The object market and players

This paper will discuss the component procurement strategies while manufacturers taking market share expansion strategy. Two kinds of procurement strategies of manufacturers were taken into considered. The first one is that manufacturers do procurement from component suppliers with spot contracts. Manufacturers and component suppliers determine the trading volume of components with the market price by negotiation after production capacity planning. They need to decide the production capacity with demand forecasting of the component market and product market and do decision making by themselves. The second one is that manufacturers do procurement from component suppliers with supply chain contracts. Manufacturers and component suppliers should determine the trading volume of components and trading price by negotiation before investment and production capacity planning. Actually, effectiveness of component procurement with both two strategies is verified on previous studies, and they have already widely used by manufacturers in practice. But in order to know the difference between the two strategies by quantification, in this paper, the independent decision making model with spot contract only and collaborate decision making model with supply chain contract were designed.

The purpose of this paper is to reveal the effectiveness of supply chain contract procurement of components while manufacturers planning the production capacity with market-share expansion strategy with the key component on its fast-growing stage. The evaluation items are considered as profit rate and market share of the manufacturer. Furthermore, the effectiveness range such as market condition and characteristics of players are also to be shown in the last part of this paper.

Literature Review

With considering of the uncertainty of trading price in spot market, the decision-making model for each collaboration level of the supplier and the buyer was proposed with using a long-term supply chain contract and a short term sales contract simultaneously. They considered a base stock policy and compared it to single sourcing options, examined the joint effect of demand and spot price uncertainty [1]. Effectiveness of the proposal was proved with comparing with the supply chain total profit. In high-tech industry, it is difficult for component suppliers to expand their production capacities with constraints of investment capital. As a result, opportunity loss of whole supply chains occur due to buyers cannot get enough volume of components to meet the needs of product demand. A contract called deductible reservation was proposed. Decision making models of players with the contract was designed. Deductible reservation contract was compared with take-or-pay contract by supply chain total profit and profit of each player. The proposed deductible reservation contract was proved as the effectiveness one between the two contracts [2]. The two studies discussed the effectiveness of long-term supply chain contract while doing decision-making of production capacity planning under uncertain market environment.

The effectiveness of contract preconditions was also discussed in many previous studies. Pay-to-delay contract set the trading volume and price to three levels, players will set their production capacity with considering of the preconditions about the level of volume and price [3]. Capacity reservation contracts between a supplier and multiple buyers originated from a project completed at a major telecommunications component manufacturer in US were discussed. Reservation fees which decided by the supplier can be deducted from the purchase price paid at delivery. Contracts between a supplier and a manufacturer involving a fixed trading price (contract price) for further purchases by the manufacturer, and a spot price determined by component market after the demand is realized in the future was discussed. Preconditions make the contract more flexible, and supplier and buyer can decide a fixed price of components by negotiation in the first step, trading volume can be adjusted in a decided range in the second step [4]. Procurement strategies combining spot market purchases with purchases based on a long-term supply chain contract. A three-parameter optimal policy was derived.

Many studies proposed a lot of new contract methods and preconditions of contract to hedge supply chain risks while players planning new production capacity, but few studies concerned the difference of procurement strategies. Uncertainties were taken into consideration in many previous studies, but the difference of uncertainties in mature market and fast growing market has not been revealed before [5-7].

Market Model

In this section, the difference of market features and uncertainties between mature product market and fast growing product market is to be discussed.

Market features

Figure 2 shows the demand transition of mature product market. There is almost no change of the average demand in such market, but demand variation occurs in each period due to the replacement needs. Figure 3 shows the price transition of mature product market. With intense price competition, market price decline occurs significantly. Variation of price also occurs in each period, because of supplydemand unbalance [8-12].

Figure

Figure 2: Demand transition of mature mkt.

Figure

Figure 3: Price transition of mature mkt.

Figure 4 shows the demand transition of fast-growing product market. Average demand grows by time. Demand variation also occurs in each period. Figure 5 shows the price transition of fast-growing product market. Because of demand growing is faster than supply growing, the market price becomes high. Variation of price also occurs in each period because of supply-demand unbalance [13-15].

Figure

Figure 4: Demand transition of fast-growing mkt.

Figure

Figure 5: Price transition of fast-growing mkt.

Market uncertainties

There are two kinds of uncertainties are taken into consideration in this paper. Figures 6-9 show the uncertainties in mature product market and fast-growing product market.

Figure

Figure 6: Center price in mature mkt.

Figure

Figure 7: Price range variation in mature mkt.

Figure

Figure 8: Center price in fast-growing mkt.

Figure

Figure 9: Price range variation in fast-growing mkt.

The first one is the center price, and the second one is the variation of price range. Market center price is a price decided by the leading manufacturer in a market. Figure 6 shows the uncertainty of center price in a mature product market. Figure 7 shows the uncertainty of variation of price range in a mature product market. The range of (L, H) changes with the fixed average demand. Figure 8 shows the uncertainty of center price in a fast-growing product market. The shadow area shows the total demand with center price which follows a normal distribution. Figure 9 shows the uncertainty of variation of price range in a fast-growing product market. The range of (L, H) changes due to the area of distribution changing with demand expansion. Both max market price H and min market price L follow the normal distributions. This paper a triangle is used to do the calculation instead of demand distribution [16,17].

Decision Making Model

In this section, the decision making model of production capacity planning with both spot contract and supply chain contract is to be discussed.

Production capacity planning with spot contract

Spot contract is a short term contract that a manufacturer does procurement of components with market price and the trading volume is decided by a component supplier and a manufacturer with negotiation. Usually, spot contract is to be connected by players after production capacity planning and investment. In this paper, contract span, contract cycle and contract bucket are set as 3 month.

With the estimated demand distribution of product market and supply distribution of component market, manufacturers do production capacity planning with expected profit and expected loss calculation. Total value of expected profit and expected loss are considered as the evaluation value. The expected loss is considered as the following two cases. (1) Demand is less than the expected supply amount of products. (2) The amount of component is less than the actual demand. Manufacturers should find out the production capacity Q with the max evaluation value. Figure 10 shows the estimated demand price distribution of product market and Figure 10 shows center price.

Figure

Figure 10: Demand price distribution.

The range of Q set as (Qmin, Qmax). Qmin can be calculated with the current share rate and total demand of market. Qmax can be calculated with the desired share rate and total demand of market. If the actual center price of product were lower than the estimated one, like Pc' in Figure 11, expected share rate becomes low as well as the profit also becomes low. Otherwise, like Pc'' in Figure 11, expected share can be achieved. Profit also becomes higher than the expected one.

Figure

Figure 11: Center price.

Relation between demand and price can be showed with formula 1 and formula 2. Angle θ is set as a parameter to show the price elasticity of the market.

D=1/2 [tan θ∙ (Pmax-P')](Pmax-P') (P' ≥ Pc)     (1)

equation     (2)

Pmax: Max price of market

Pmin: Min price of market

P': The actual price in the future

Pc: Center price

Dmax: Average total demand of market

Figure 12 shows the relation between supply and price of component market. Figure 13 shows the price rise risk in the component market which occurs by short supply to this product market.

Figure

Figure 12: Supply price distribution.

Figure

Figure 13: Price rise with short supply.

With considering of the risk and return in product market and component market. Expected profit and expected loss and value can be calculated with the formulas below:

equation     (3)

equation     (4)

Value=Expected profit + Expected loss     (5)

Q: Candidate production capacity Q=Q0 (1+r)

Q0: Current production capacity

r: Desired share rate for next term

q: Actual sell amount, set it as q=1/2(Q-Q0)

Ppc': Center price of product market

Pcc': Center price of component market

Ppmin: Minimum price of product market

Pcmax: Maximize price of component market

Costm: Production cost of manufacturer

After the calculation, the manufacturer will set the production capacity for next term as Q with the best value. After production capacity preparation, the manufacturer will make the order Q to the supplier.

Production capacity planning with SC contract

Supply chain contract is a long term contract that a component supplier and a manufacturer decide the trading volume and trading price of components at an early time before production capacity planning and investment by negotiation. In this paper, contract span, contract cycle and contract bucket are set as 48 month, 12 month, and 3 month.

In this paper, supply chain contract parameters are set as max trading volume, min trading volume and the trading (contract) price. The manufacturer decide the min purchasing volume, the component supplier decide the max supply volume. The trading price is to be decided by the two players with negotiation.

The min purchasing volume can be considered as the current production volume Q0. So the manufacturer set the min purchasing volume as Q0. Besides Q0, he also has to inform the supplier the expected supply volume Q of product with the desired market share rate. After achieving Q and Q0, with estimated distribution of demand and price, the component supplier will decide the max trading volume.

Max trading volume and min trading volume can be calculated with the formulas as below:

Qmin=Q0    (6)

Qmax=[(1-R) Qmin Pcc' ]/Costs    (7)

R: Expected profit rate of component supplier

Costs: Production cost of component supplier

With the max trading volume and the min trading volume, supplier and manufacturer will decide the trading price with negotiation. It is necessary for the two players to do profit and loss calculation during the negotiation. In this paper, to simplify the negotiation process, middle price of expected price of the two players are considered as the trading price.

With considering of the risk and return in product market and contract parameters. Expected profit and expected loss and value can be calculated with the formulas below:

equation     (8)
equation     (9)

Value=Expected profit + Expected loss     (10)

Q: Candidate production capacity Q ∈ (Qmin, Qmax)

After the calculation, the manufacturer will set the production capacity for next term as Q with the best value. So, the range of order is (Qmin, Q).

Experiment

In this section, experiments and results are to be discussed.

Experiment instructions

Firstly, profit rate while the manufacturer taking share up strategy in the mature product market were confirmed. Secondly, spot procurement and supply chain procurement with share rate to confirm the effectiveness of supply chain procurement in this kind of situation were compared. Trading period were set as 4 terms (48 month).

Results

In the following section shows the result of simulation.

Figure 14 shows the profit achievement of the manufacturer with spot procurement and supply chain procurement. Profit becomes low in accordance with the time. But, in each term, profit achievement with supply chain procurement is more than spot procurement. There are two reasons. The first one is risk hedging during the decision-making of production planning almost occurs in the first half of the whole period. The second one is the problem of balance carried forward almost occurs in the second half of the period.

Figure

Figure 14: Profit rate comparison.

It is difficult for the manufacturer to expand share sustainably when deficit occurs due to the problem of balance carried forward. So, the manufacturer is considered that he could not get survived while deficit occurs. During the experiment, probability of deficit with spot procurement is much higher than supply chain procurement. Figure 15 shows the comparison about the rate of failure with these two procurement methods. Once budget deficit occurs, share up expansion failure occurs. In most cases, deficit occurs from term 3 and term 4. In term 3, rate of failure is much lower by decision-making with supply chain procurement.

Figure

Figure 15: Rate of failure.

Figure 16 shows the share rate with these two procurement methods in each trading term. It is difficult for spot procurement to expand the desired share rate of manufacturer. Especially, with the price competition of product market becoming heavy, the share rate may become lower than the initial value. The desired share rate can be considered as a characteristic of the manufacturer. An optimistic manufacturer may set a higher desired share rate and do production planning positively. So, it is better for these manufacturers to purchase components with supply chain contract in a high uncertainty market.

Figure

Figure 16: Share rate comparison (Term End)

Discussion and Conclusions

In this paper, uncertainties in mature market and fast growing market were defined. Also, the model of short-term spot contract and long-term supply chain contract were created. After that, the manufacturer’s decision-making models of production capacity planning with both component procurement methods were designed. Do procurement of key components in a fast growing market with high uncertainties and supply the finish product to a mature market with heavy price competition is very difficult to manufacturers. In this kind of situation, in order to get a long survival period in the product market, it is better for the manufacturer to do investment to expand the market share with connecting a long-term supply chain contract with a fixed supplier.

With the market model and the decision making model, evaluation items of profit achievement, failure rate and share rate expansion were taken into consideration to do the comparison between spot procurement and supply chain procurement. The effectiveness of production capacity planning with considering of share rate up strategy was proved by using of the supply chain contract quantitatively.

Preconditions setting such as max trading volume, min trading volume and trading price are considered to improve the supply chain efficiency. Tasks such as negotiation process improvement, different desired share rate setting with different market situation are to be discussed in our future studies.

References

Select your language of interest to view the total content in your interested language
Post your comment

Share This Article

Relevant Topics

Article Usage

  • Total views: 10387
  • [From(publication date):
    June-2016 - Jul 16, 2019]
  • Breakdown by view type
  • HTML page views : 10138
  • PDF downloads : 249